Majene

Wednesday December 18, 2019 | 15:49

Kampus mangkrak Unsulbar/Sulbarkita.com-Ashari

Majene, Sulbarkita.com - After long being a byword of the people, the Majene District Attorney finally investigated the case of the construction of the campus of the University of West Sulawesi (Unsulbar), in the Padha - Padhang neighborhood, East Tande Sub-district, East Banggae District, Majene Regency, West Sulawesi.

Head of the Attorney General's Intelligence Section Majene Muhammad Ikhsan claimed to have come to the Unsulbar campus to see firsthand the condition of the building. Ikhsan also requested information from the party suspected of knowing the cause of the project's stalling. "One of the questions requested was the PPK (Official Commitment of the Unsulbar Campus Project Commitment)," Ikhsan said via Whatsapp message to Sulbarkita.com on Monday 9 December 2019.

The Unsulbar campus in the Padha-Padhang neighborhood was built in 2016, three years after the university was designated as a State University (PTN). However, the construction of the campus, which was supported by funds from the Ministry of Research, Technology and Higher Education (Kemenristekdikti) of Rp 3.1 billion, was actually stalled. As a result, most lecture rooms cannot be used until now.

Baca juga:
Ironi Kampus Unsulbar, Menara Gading Dibalut Belukar
Gerakan Sejuta Koin untuk Kampus Mangkrak Unsulbar

Sulbarkita.com briefly reported on the current condition of the Unsulbar building. Most of the buildings are still in the form of concrete frames coated with rough cement. These conditions make students concerned and ask for contributions to the community to build Unsulbar on a number of protocol roads in Majene.

Also read:

Ikhsan claimed to have followed the news about the campus. Therefore, the Prosecutor's Office immediately conducted a search to Unsulbar when he received information about the stalling of the project. "The final conclusion is that the conditions are due to the budget to continue development activities only this year," he said. "Later we will create a team to monitor the implementation of the project."

Chancellor of the University of West Sulawesi Aksan Djalaluddin confirmed that the Prosecutor's Office had visited his campus. However, Aksan claimed that the arrival of the Prosecutor's Office was a normal visit. "Yes, indeed (they came) there but that we ask for escort as TP4D (Team Guards and Safeguards of the Government and Regional Development)," Aksan said when confirmed by Sulbarkita.com on Tuesday 17 December 2019.

The former Head of the West Sulawesi Agriculture and Animal Husbandry Service also admitted that some of his subordinates were questioned by the Prosecutor's Office. "His name is also escort so certainly questioned," said Aksan.

Aksan stressed that the construction of the Unsulbar building in Padha-Padhang will continue in the near future. According to him the project tender is still proceeding at the Regional Infrastructure Development Center and PUPR Construction Services in West Sulawesi. "Let's just wait for the process to be completed," Aksan said.

Reporting from Antaranews.com, Kejari Majene also conducted an investigation into the alleged corruption of the Unsulbar development project for the 2012 fiscal year. Former Acting Head of the Cipta Karya Department of Public Works, West Sulawesi, Mukaddam was arrested in the case in April 2013.

"After conducting an intensive examination for six hours, Majene Majari investigators finally arrested the suspects of corruption in the construction of lecturer dormitories, halls and guesthouses of Unsulbar who were domiciled in Majene," said Majasi Majid Pidsus Chief, Awaluddin at the time.

Muhamaad Ashari



Comments For This News (0)