Polewali Mandar, Sulbarkita.com — An abrasion barrier (TPO) at the Mampie Beach, Galeso Village, Wonomulyo Subdistrict, Polewali Mandar continued to reap polemics in the past few days. Because the project valued at Rp. 7.4 billion was allegedly not in accordance with the building materials required in the planning.
One of them is stone in the TPO project. Usually, the type of stone used to make TPO is a boulder elephant stone or often called a complete elephant stone. So that it firmly withstand abrasion on the beach.
But in the TPO project at Mampie Beach, CV Triga Cipta Abadi as the winner of the tender used elephant rock that had been broken down or a breaker. So that it is not only suspected not to be in accordance with the standards, but the level of robustness of the project is questionable.
Polman Regent Andi Ibrahim Masdar claimed to have received a report regarding the condition of the project. He also asked PT Triga to work on the project according to the standards contained in the Budget Plan (RAB). "In essence, I do not agree that there are projects that do not work according to the bestek and drawings," the Regent said on Monday, June 17.
Ibrahim emphasized that the TPO project should use a type of elephant rock that is still intact. "The name of the elephant stone is a stone that is as big as an elephant, if it is broken, it is more feasible to make a home foundation," he said.
Sulbarkita.com also immediately checked the condition of the project. In Mampie, there are two TPO projects carried out in 2019. The first project is 100 times 100 meters while the second project is 30 times 20 meters. The second project is located right in the tourist attraction of Mampie Beach.
From the observation of Sulbarkita.com, the project is indeed using elephant stone, but it has been broken down by an alias breaker. The average size of the stone is a ball of foot or about 20 centimeters.
The size of the stone in this project is different from the size of a similar project funded by the central BNPB in the same location. In the project that was carried out two years ago, the elephant rock used is still intact aka not broken down. The size starts from 2 meters to 2.5 meters.
Seeing this comparison, local residents were worried that CV Triga's TPO would not last long. "The broken stone is easily weathered," said Asyari.
TPO project consultant Mampie Mawardin when confirmed confirmed that the most widely used stone was the elephant rock that had been broken. But he argued that the stone only served to lock the whole elephant stone that had been installed first on the seabed. "It has been based on project specifications," he said when he was met at the project site on Friday, June 14.
Reski, the project executive, also said the same thing. According to him, the use of broken stones to fasten the stones which are still perfectly intact in the TPO project. "Because it is impossible to use all large stones," he said.
The TPO project was indeed encouraged in Polman in recent years. Because abrasion in this district is quite severe. For example in Panai Mampie, from the records of the National Disaster Management Agency (BNPBD) Polman in the period of 2017 to 2019 as many as 15 meters of land in Dusun Mampie were lost due to abrasion.
AHMAD G